Availability × utilization × recovery: three uncertainties that multiply.powered by Vose Software
← Mining calculators

Your plant is designed for 3 Mtpa. You'll achieve 2.4 Mtpa. Here's why.

Processing plant performance depends on three multiplicative factors: mechanical availability (uptime after breakdowns), utilization (time actually processing when available), and metallurgical recovery (metal extracted from ore). Each factor has its own uncertainty, and the product of three uncertain quantities has a wider distribution than any single factor. A plant designed for 92% availability × 95% utilization × 88% recovery = 77% overall efficiency. But the P10 of these three factors multiplied is often 60-65%.

Why this requires Monte Carlo simulation

The product of three independent uncertain variables (each Beta or PERT distributed) has no closed-form distribution. The distribution is skewed even if individual factors are symmetric, because downside scenarios compound multiplicatively. Simulation samples each factor independently and computes the product, revealing the true distribution of metal output — which is always wider and more left-skewed than a single-factor analysis suggests.

Plant design parameters
Design throughputMtpa

Availability (% of calendar time)
Utilization (% of available time)
Recovery (%)
Head gradeg/t

Enter plant parameters and run.