Your optimal pit changes shape at different prices. Which price do you design for?powered by Vose Software
← Mining calculators

The optimal pit at $2,200/oz gold contains 35Mt. At $1,700/oz, it shrinks to 22Mt. You have to commit to one design.

Open pit optimization (Lerchs-Grossmann or floating cone) produces a nested set of pit shells — each optimal at a different revenue factor (commodity price). The shell at a high price is larger (lower cut-off, more waste), while the shell at a low price is smaller and higher grade. The mine design must commit to one ultimate pit shell, but the commodity price over a 15-20 year mine life is profoundly uncertain. Choosing the wrong pit shell — too large if prices fall, too small if prices rise — is an irreversible decision.

Why this requires Monte Carlo simulation

Each candidate pit shell produces a different mine plan with different tonnage, strip ratio, grade profile, and capital requirements. The NPV of each shell depends on the commodity price path over the mine life. To find the robust optimal shell, you must simulate NPV across price paths for each candidate shell — a two-dimensional optimization (shell selection × price uncertainty) that requires Monte Carlo.

Pit shell options
Each shell is optimal at a different price. Enter the characteristics of 4-5 nested shells.

Commodity price ($/oz over mine life)
OPEX$/t processed
Mining cost$/t total moved
Recovery%
Discount rate%

Configure pit shells and run.