Exploration drilling reduces geological uncertainty — but at a cost. The value of information (VOI) framework asks: "How much would I pay to have perfect (or improved) information before making my investment decision?" If the answer exceeds the drilling cost, the program is justified. For mining, the decision being informed is usually "proceed to feasibility" vs "walk away" — and the cost of being wrong (building a mine on an inadequate resource) is enormous.
VOI requires computing the expected NPV of the project under current uncertainty, then computing the expected NPV with reduced uncertainty (after drilling), and taking the difference. The "reduced uncertainty" state requires simulating the drill program's impact on grade and tonnage confidence intervals — a simulation within a simulation. The VOI is the expected gain from improved decisions, which can only be computed by simulating both the "drill" and "don't drill" decision paths.
Enter parameters and compute the value of information.