Three-point estimating is the most common technique in project risk analysis. You ask an expert for optimistic, most likely, and pessimistic values. But then what? The Triangle distribution (the textbook default) puts too much weight on the most likely value and has linear tails that cut off abruptly. The PERT distribution is smoother and more realistic. The Lognormal captures the right-skewed nature of cost uncertainty but ignores the most likely value entirely.
The choice of distribution matters more than most practitioners realize. For contingency calculations, the difference between Triangle and PERT at the P80 level can be 10-20% — which translates directly into whether your contingency is adequate or not.
When you add 20-50 three-point estimates together (as in a full cost estimate), the Central Limit Theorem smooths out the differences somewhat. But it doesn't eliminate them — the aggregate distribution's shape, skewness, and tail percentiles depend on the distributional assumption used for each line item. The only way to see this effect is to simulate the full cost model with each distribution type and compare the aggregate results. Analytical formulas exist for means and variances but not for the P80 of a sum of PERT-distributed variables with different parameters.
Enter your three-point estimate and compare distributions.