Scope changes add 15-25% to most projects. Your risk model probably ignores them.

Risk registers capture identified technical risks. But the #1 cause of cost and schedule overruns on major projects is scope change — additional work that wasn't in the original estimate. Scope changes are a random process: they arrive over time, each with uncertain cost and schedule impact. The total impact depends on how many changes occur and how large each is — a classic compound process.

Why this requires Monte Carlo simulation

Scope change impact follows a compound Poisson model: N changes arrive (Poisson distributed), each with uncertain cost (PERT or Lognormal). The aggregate is a compound distribution with no closed form. The timing of changes also matters — early changes cost less than late changes due to the ripple effect through downstream activities. Simulation captures both the random count and the random individual impacts.

Scope change model
Base project estimate$M
Expected scope changescount over project life
Industry average: 8-15 material scope changes per major project
Cost per change$M
Late-change cost multiplier (max, at project end)
Cost multiplier grows quadratically with timing: 1× at project start, ramping smoothly to this value at project end.

Configure and run the scope change analysis.