Your critical path changes in 40% of scenarios.powered by Vose Software
← Project Risk calculators

Your CPM schedule shows 18 months. But in 40% of simulations, a different path goes critical — and the project takes 24 months.

Critical Path Method (CPM) identifies the longest path through your schedule network — at deterministic durations. But when activity durations are uncertain, the critical path itself becomes uncertain. An activity with 5% total float in the deterministic schedule might be on the critical path in 30% of Monte Carlo iterations if its duration is right-skewed. This "criticality index" is invisible in a deterministic schedule.

The result: your schedule contingency should be based on the P80 of the simulated project duration, not the deterministic critical path + a percentage buffer. The two numbers can differ by 20-40%.

Why this requires Monte Carlo simulation

Schedule risk analysis requires simulating the entire network: for each iteration, sample all activity durations, perform a forward/backward pass to find the critical path, and record the project completion date. The critical path changes between iterations because different activities "win" the race to be longest. The probability distribution of project duration — and the criticality index of each activity — can only be computed by simulation. There is no analytical formula for the percentiles of the maximum of correlated sums of random variables along different paths.

Activities (simplified serial/parallel network)
Path: which parallel track (A or B). Activities on the same path are serial.

Schedule contingencymonths