Critical Path Method (CPM) identifies the longest path through your schedule network — at deterministic durations. But when activity durations are uncertain, the critical path itself becomes uncertain. An activity with 5% total float in the deterministic schedule might be on the critical path in 30% of Monte Carlo iterations if its duration is right-skewed. This "criticality index" is invisible in a deterministic schedule.
The result: your schedule contingency should be based on the P80 of the simulated project duration, not the deterministic critical path + a percentage buffer. The two numbers can differ by 20-40%.
Schedule risk analysis requires simulating the entire network: for each iteration, sample all activity durations, perform a forward/backward pass to find the critical path, and record the project completion date. The critical path changes between iterations because different activities "win" the race to be longest. The probability distribution of project duration — and the criticality index of each activity — can only be computed by simulation. There is no analytical formula for the percentiles of the maximum of correlated sums of random variables along different paths.
Configure activities and run.