Qualitative risk registers (5×5 probability-impact matrices) are ubiquitous. But they have a fatal flaw: they cannot be aggregated. You can't add "High" + "Medium" + "Low" to get a total risk exposure. When the board asks "what is our total cost risk?", the risk manager has to guess — usually underestimating because they add expected values rather than simulating the full distribution.
Quantifying each risk as a probability × impact distribution and simulating the portfolio reveals the true aggregate risk exposure — including the crucial "how many risks actually materialize simultaneously?" question that qualitative methods cannot answer.
Each risk event has a probability of occurrence (Bernoulli) and an uncertain impact if it occurs (PERT or similar). The total risk exposure is the sum of these compound random variables. With 15+ risks, some correlated, the aggregate distribution has no analytical form. Worse: the "maximum plausible loss" (the scenario where multiple risks co-occur) is what drives contingency — and this can only be computed by simulating which combinations of risks occur together.
Enter your risks and quantify.