When you have 8 candidate projects and budget for 5, the naive approach is to rank by NPV (or benefit-cost ratio) and fund the top 5. But this ignores budget constraints (some projects cost more), synergies and dependencies, and the risk profile of the portfolio. The optimal subset of 5 may not include the highest-NPV project if it's expensive and displaces two smaller, collectively more valuable projects.
Finding the optimal portfolio requires evaluating all C(8,5) = 56 possible subsets (or 2⁸ = 256 if partial funding isn't required). For each subset, you need the uncertain portfolio value — which depends on the correlation structure between project outcomes. Monte Carlo simulates each candidate portfolio to compute expected value, risk, and efficiency, then identifies the optimal frontier.
Configure projects and run.