CPI=0.92 doesn't mean you're almost on budget.powered by Vose Software
← Project Risk calculators

Your EVM says EAC = $52M. The 90% confidence interval is $48M to $63M.

Earned Value Management gives a single EAC (Estimate at Completion) based on CPI and SPI. But these indices are themselves uncertain — they fluctuate from period to period and may not be stationary. A CPI of 0.92 from 30% progress gives a less reliable EAC than a CPI of 0.92 from 80% progress. The uncertainty in EAC should narrow as the project progresses — but standard EVM formulas don't show this.

Why this requires Monte Carlo simulation

The EAC formula (BAC/CPI or ETC + AC) is a point estimate from a ratio of random variables. The sampling distribution of CPI depends on the number of periods observed, the variance in period-to-period performance, and potential trends. Monte Carlo simulates future period performance from the observed distribution to produce a forecast range, not a single number.

Project status
Budget at Completion (BAC)$M
Actual Cost to date$M
Earned Value to date$M
% complete
CPI period-to-period variability (CV)
How much does CPI fluctuate period to period? 0.1=stable, 0.3=volatile
Total planned periods (baseline)
Planned project length in periods (months/weeks). Used for schedule forecast.

Enter EVM data and run the forecast.