Earned Value Management gives a single EAC (Estimate at Completion) based on CPI and SPI. But these indices are themselves uncertain — they fluctuate from period to period and may not be stationary. A CPI of 0.92 from 30% progress gives a less reliable EAC than a CPI of 0.92 from 80% progress. The uncertainty in EAC should narrow as the project progresses — but standard EVM formulas don't show this.
The EAC formula (BAC/CPI or ETC + AC) is a point estimate from a ratio of random variables. The sampling distribution of CPI depends on the number of periods observed, the variance in period-to-period performance, and potential trends. Monte Carlo simulates future period performance from the observed distribution to produce a forecast range, not a single number.
Enter EVM data and run the forecast.