A deterministic cost estimate sums the "most likely" value for each work package. But this sum is the mode of the total cost distribution, not the mean, and certainly not the P80 that should drive your contingency. For right-skewed cost items (which almost all are — things go over budget more often and by more than they come in under), the sum of modes systematically understates the expected total cost.
The gap between the deterministic estimate and the P80 is your cost contingency requirement. If your contingency is based on a percentage of the base estimate ("add 15%"), you're guessing. Simulation tells you the actual number — and which work packages drive the most risk.
The sum of 20+ PERT-distributed work packages with different skewness parameters has no analytical solution for percentiles. Even the variance of the sum depends on correlations between work packages (shared labor rates, weather delays, same contractors), which further complicate the calculation. Monte Carlo samples each work package independently (or with correlations), sums them, and directly computes the total cost distribution — including the P80 that determines your contingency.
Edit the WBS and run the cost simulation.