Contingency setting in practice is often a political negotiation: the project team asks for 20%, the board offers 10%, they compromise at 15%. This has no connection to the actual risk. A proper contingency is the difference between the base estimate and the target confidence level (usually P75-P85) of the cost distribution. It depends on the number of cost items, their individual uncertainty ranges, and the correlations between them.
Projects with few large, uncertain items need more contingency (as a %) than projects with many small, well-understood items — because diversification works for cost estimates just like for financial portfolios. A 100-item estimate with 15% average uncertainty per item might only need 8% contingency, while a 10-item estimate with the same average uncertainty might need 20%.
The required contingency percentage depends on the shape of the aggregate cost distribution, which depends on the number of items, the skewness of each, and the correlations. No simple formula captures this correctly. The common "square root of sum of squares" formula assumes Normal distributions and independence — both wrong for cost estimates. Only simulation handles arbitrary distributions with correlations.
Enter your project profile and check your contingency.