Offshore decommissioning is a growing global liability exceeding $100B. Operators must carry provisions on their balance sheet, but these provisions are typically point estimates at an assumed cessation of production (CoP) date. Both are wrong: cost estimates for decommissioning routinely understate by 30-50% (because they're based on limited precedent), and CoP timing depends on oil price, production decline, and regulatory decisions that are inherently uncertain.
The interaction between timing and cost uncertainty is nonlinear through discounting: a 5-year delay in CoP reduces the present value of the liability significantly — but also allows costs to escalate. The net effect depends on the discount rate vs cost inflation rate, which is itself uncertain.
The present value of decommissioning cost = Cost(CoP) / (1+r)^CoP, where both Cost and CoP are uncertain and potentially correlated (later decommissioning may face stricter regulations and higher costs). This is a ratio of two uncertain quantities raised to an uncertain power — a highly nonlinear function with no analytical solution. Simulation samples all three uncertainties jointly to produce the correct PV distribution.
Configure your asset and run the simulation.